Monday, June 6, 2011

Stucco

The outside of the house has been a complete wreck for quite sometime. Where the old house met the new foundation - quite a few patches appeared in the stucco. Plus adding and removing windows played a little havoc with the exterior. So we hired Sergio to fix it. The outcome was average. However with a nice new paint job, the house looks much brighter and cleaner than before. We plan to add trim around the doors and windows and paint them all blue. Should look nice!!!



Patchy and snowy

The outside had this black paper up over the winter - which kept it waterproof - but ugly.



New stucco going around the old stucco - pulling the old down and starting with a completely clean canvas would have been the ideal situation, but unfortunatley not in our price range!


Not a big fan of the texture!





New paint - starting to look better!


I spy Chris fixing the venting

Looking clean and fresh with the new paint - just need to get a garage door!

View from the back of the house - hazy background is smoke from the wildfires in AZ - its been like it all weekend!

Thursday, December 30, 2010

Christmas

Don't have to much to write - so here are some pictures of how the house looked on Christmas. Not liveable. Not Christmasy. Not what we had hoped it would look like - but on a positive note, progress continues to be made!!

View of the Kitchen. Drywall has has been taped and mudded. Corner beads in place.

Living area and stairway to basement

Bathroom - shower has been cement boarded and drywall completed. Need to tile the floor and shower.

Corridor towards living area. Firewall on left needs one more layer of drywall!

Chris made a garage door - so the house is now completely enclosed. Url's butt in view!

Wednesday, December 22, 2010

Drywall

Once the blown insulation was completed by the pro's - Chris and I got to the interior walls with some fiberglass. At the same time the guys got to work with the drywall. By the end of the weekend - good progress had been made. Hopefully by Christmas the whole upstairs will be drywalled, and ready for primer and paint !!!! Thats going to be an exciting day!

Rather them than me. So thankful for these talented guys!

Screwing the drywall in place

Chris and Url watching!!

The last of the free windows - perfect size and shape for the master bedroom - and lovely view of the back garden.

At the front of the house - wheres url ???
Impossible to hide with those ears!

A fiberglass frock. Itchy!
Cutting and stapling the interior insulation!

Drywall in the corridor

Kichen starting to get covered!

Spare bedroom

Bathroom ceiling going up

Corridor ceiling in!

Lots of snow outside the back door!!

Tuesday, December 14, 2010

Insulation

The framing was complete. Next step - insulation. We decided on blown insulation because three of our exterior walls were only 2 by 4's - so maximum R value would only have been R-15. Not ideal when temperatures outside get pretty darn cold. With the blown - which is made up of chopped newspaper - we could get an R value of 20. For the ceiling it would be R-50!! Plus we wouldn't have to deal with the itchyness of fiber glass -  it was therefore an easy decision! So yesterday and today our insulation guys got to work, and started making the house nice and toasty!


Firewall done.

Exterior walls and ceiling done

New front windows in and walls insulated!

Blown insulation between studs.

Plastic making a good, level base for the R-50 insulation!

Double toastyness !! Blown insulation and the roaring pellet stove!!

Sunday, November 14, 2010

Progress.

November 14th - this is how the house is coming along thus far.
  • All the cement for walls and footers have been poured. Only slab (floor) left to pour. 
  • All walls in the house have been framed, including closets in both bedrooms.
  • Every wall in the house has had drywall and old insulation removed. 
  • Fire wall framed, outside wall finished. Awaiting insulation and drywall inside. 
  • New floors laid throughout except for small section at the front door.
  • Staircase to basement underway. 
  • Plumbing - 'rough in' underway. 
  • Ceilings dropped, leveled and framed thoughout (thanks to Walt, Christian and Chris today)
  • Electrician starting this week (we hope)
  • Kitchen cabinets, appliances and granite counter-tops ordered. 
  • Tiles for the bathroom bought - a super nice, grey limestone. 
  • One of eight windows replaced. 

Lovely blue front door and new window in place. The door is a slightly odd shape and therefore does not fit the door frame well - so unfortunately we will probably have to get a different one.

Staircase into basement being built

View from basement

The very back wall of the new basement finished.

The lowest framing seen is the new level ceiling.

New double shower tray bought and in place! We will tile the walls

Fire wall from outside finished. Just needs the stucco now!

Walt helping with the ceiling today - couldn't have finished it so quickly without him - thanks!!

Walt and Christian measuring.

They were there till dark - but got the whole ceiling framed in a day!!

I pulled down the remaining drywall and insulation from the far corner of the house - I took a picture afterwards. It looks like its snowing inside the house - or I don't have a great camera - but actually this is the dust in the air - captured by my flash. Gross.

While the cats away....

I went to England. Chris took a week off work and worked on the house.
Progress was good. Most of the floor was laid. The roof was supported. Walls were framed. The fire wall went up. More cement was poured. The construction site I left looks more like an actual house now. I should go away more often!

Center framing still there to support the roof. Flooring in center of the house almost done!

The plank into the house

Some of the dry wall was removed!

New beam across to support the roof

Framing of the new rooms almost finished!! Plank still in place though! View of where the kitchen/living will be - and then second bedroom plus corridor.

Fire wall fully underway. New back door framed!

Step up to Master bedroom - New floor laid, and new wall framed!

This is the original (outside) wall of the bathroom - please note the slightly unlevel framing! Unique to say the least!